Pre Design-SLD for the first 54 MW
18 MW Phase 1 Capacity is Pre-Designed to accommodate 10 MW (5X2MW) + 6 MW (3X2 MW) + 2 MW (1+1). The capacity of planed units is subject change as per SPD’s requirements
Features
- Solar Plant Cost at Aram Solar Park will be lower than Independent IPP
- No challenges to SPG – Single Window Clearance and Services
- Project Location is well connected with Road, Rail & Airport and Sea port.
- Ideal for passive investors with attractive ROI
- Project ideal for Captive and Open Access Consumers
Status
- Land aggregation
- First 54 MW – aggregation completed
- Second 54 MW – Partially aggregated. Balance in progress.
Services Offered to SPG
- Turnkey Single Window Solutions for Project Developers on structured scheme and price
- Structured Project Implementation
- Term Loan can be arranged – separate terms
- Flexible for participatory – transparent – project costing on open margin basis
- Major equipments can be supplied by the SPG – upon mutual acceptance